Provision a Data Center in 30 days
Sunday, November 29, 2009 at 10:30AM
Gary L Kelley in Data Center, Data Center Design, IT

This is not some cleverly named cloud computing article. This was a real requirement.
(I will leave the details around how this company got in the situation of needing a data center in 30 days….clients find themselves in situations from time to time, either due to growth, capacity, or outages.)

The key to performing data center miracles rests with the network. If the network is near the facility, you’re golden.

This company had two main wide area network vendors (household name companies), and two major ancillary metropolitan area network providers. We felt we would have no issue finding a co-location site within the geographic boundaries some of the technologies required.

In this particular case, we needed a modest “cage” in a larger facility. We came up with our short list fairly quickly, and promptly went out and toured facilities. One facility percolated quickly to the top of our list; two of our network providers were there, the facility was in walking distance of another one of the company data centers, and we discovered the facilities manager was a alumni of a past employer.

This started a massive parallel effort.

The staff was fully brought into the decision, the business need, and helped plan the transition. Circuits, servers, storage arrays, etc. were all ordered immediately as the contract with the co-lo facility was worked out. Hardware vendors are used to performing miracles; they often install a large amount of equipment leading up to their quarter end.

While all vendors began responding, one communications vendor balked. They had a process, and as a part of that process had timeframes, and those timeframes were incontrovertible. We met with the vendor, and you could almost see the “A crisis on your part does not create a crisis for me” sign on their foreheads.

We went to the other communications vendors not in the building and made our case. One company, a scrappy start up charged with selling communications along utility rights of way, acknowledged have services “in the street,” but would have to get approvals from the City. (Full disclosure. This was Boston during the Big Dig. Every street was torn up on a tightly coordinated plan. The issue wouldn’t be getting the approvals, it would be getting Big Dig approvals.)

One thing scrappy start ups often have going for them is they are nimble. This supplier had the street open within a week (at night, no less), and brought new facilities into the colo site. It was good for us, and over time they certainly got additional business.)

Following the same process and using vendors used before allowed us to accelerate the delivery. The electricians “knew” what we wanted (once we gave them requirements,) the cable plant was put in by the usual suspects, the security department deployed full badge readers and security cameras, etc.

By following the same processes, our team was able to deploy on a predictable basis. Certainly some long nights were required, and this was a sacrifice made by the staff. Since they understood the business need and Information Technology imperative, they responded with aplomb.

And the facility was up and running on time.

Processes and engagement allowed the IT area to meet the business need. Processes run amok had one communications vendor wondering what happened.

By focusing on repeatable and timely process, this excellent team delivered!

Article originally appeared on Gary L Kelley (http://garylkelley.com/).
See website for complete article licensing information.